πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR Β· WEST

Solar project SGI-PNM-2022-04, Grant County

Solar project SGI-PNM-2022-04, Grant County is a 5.0 MW solar request withdrawn in the West interconnection queue, in Grant County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedJun 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
SGI-PNM-2022-04
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Tyrone Substation Distribution Feeder 395
Location
Grant County, New Mexico
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
9 December 2021
Proposed online date
December 2023
Withdrawn
June 2022

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem