United States βΊ Grid βΊ Interconnection queues βΊ Oregon
SOLAR Β· WESTSolar project 828, Lake County
Solar project 828, Lake County is a 13.0 MW solar request withdrawn in the West interconnection queue, in Lake County, Oregon, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedOct 2019 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 828
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Bullard substation
- Location
- Lake County, Oregon
- Technology
- Solar: 13.0 MW
- Total requested
- 13.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA executed 10/1/19, Terminated
- Queue status
- Withdrawn
- Entered queue
- 21 November 2016
- Agreement signed
- 1 October 2019
- Proposed online date
- November 2019
Location
Marker shows the centre of Lake County; the queue data does not give exact sites.
Other requests in Lake County
- Solar + storage project G0841, Lake CountySolar + storage Β· 600 MW Β· in study
- Onshore wind project G0870, Lake CountyOnshore wind Β· 500 MW Β· in study
- Onshore wind project G0871, Lake CountyOnshore wind Β· 500 MW Β· in study
- Solar project G0651, Lake CountySolar Β· 400 MW Β· in study
- Solar + storage project C2-152, Lake CountySolar + storage Β· 320 MW Β· in study
- Solar + storage project C2-182, Lake CountySolar + storage Β· 320 MW Β· in study
- Solar + storage project C2-187, Lake CountySolar + storage Β· 320 MW Β· in study
- Solar project G0655, Lake CountySolar Β· 200 MW Β· in study
- Battery storage project PIS096, Lake CountyBattery storage Β· 200 MW Β· in study
- Solar + storage project C2-173, Lake CountySolar + storage Β· 199 MW Β· in study
- Battery storage project C2-171, Lake CountyBattery storage Β· 199 MW Β· in study
- Battery storage project C2-170, Lake CountyBattery storage Β· 199 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem