United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Itsee Solar

Itsee Solar is a 52.9 MW solar request withdrawn in the ERCOT interconnection queue, in Navarro County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2021 (completed)
  2. Withdrawn / abandonedFeb 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
25INR0024
Grid region
ERCOT (Texas)
Developer
Gransolar Texas Seventeen, LLC
Connection point (POI)
Trinidad Switch β€šΓ„Γ¬ Long Prairie Switch 138 kV
Location
Navarro County, Texas
Technology
Solar: 52.9 MW
Total requested
52.9 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
11 October 2021
Proposed online date
July 2027
Withdrawn
February 2025

Location

Marker shows the centre of Navarro County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Navarro County