United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

ONSHORE WIND Β· SPP

Onshore wind project GEN-2010-045, Ford County

Onshore wind project GEN-2010-045, Ford County is a 198 MW onshore wind request withdrawn in the SPP interconnection queue, in Ford County, Kansas, connecting to SUNC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2010 (completed)
  2. Withdrawn / abandonedApr 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2017 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2010-045
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
TAP HOLCOMB β€šΓ„Γ¬ SPEARVILLE 345kV
Location
Ford County, Kansas
Technology
Wind: 198 MW
Total requested
198 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 September 2010
Proposed online date
December 2017
Came online
December 2017
Withdrawn
April 2018

Location

Marker shows the centre of Ford County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Ford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem