BATTERY STORAGE · WEST

Battery storage project Q82, Los Angeles County

Battery storage project Q82, Los Angeles County is a 300 MW battery storage request in interconnection study in the West interconnection queue, in Los Angeles County, California, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Jul 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q82
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Gramercy-Harbor 138kV Line
Location
Los Angeles County, California
Technology
Battery: 300 MW
Total requested
300 MW
Study phase
Application received
Queue status
Active
Entered queue
29 July 2021
Proposed online date
May 2024

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County