πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AG2-560, Clearfield County

Solar project AG2-560, Clearfield County is a 19.9 MW solar request withdrawn in the PJM interconnection queue, in Clearfield County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-560
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Developer
Morrisdale Solar IV, LLC
Connection point (POI)
Phillipsburg (Karthaus) 34.5 kV
Location
Clearfield County, Pennsylvania
Technology
Solar: 19.9 MW
Total requested
19.9 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
31 March 2021
Proposed online date
April 2025
Withdrawn
January 2025

Location

Marker shows the centre of Clearfield County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Clearfield County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem