BATTERY STORAGE Β· CAISORichgrove
Richgrove is a 207 MW battery storage request withdrawn in the CAISO interconnection queue, connecting to SCE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2023 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 54539
- Grid region
- CAISO (California)
- Utility / transmission owner
- SCE
- Connection point (POI)
- WHIRLWIND 230 kV
- Location
- California
- Technology
- Battery: 207 MW
- Total requested
- 207 MW
- Service type
- Network resource (NRIS)
- Study phase
- Caiso Cluster 15 Unvalidated
- Queue status
- Withdrawn
- Entered queue
- 17 April 2023
- Proposed online date
- June 2028
- Withdrawn
- December 2024
Location
Marker shows the centre of County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in County
- Rexford 2 Solar FarmSolar + storage Β· 400 MW Β· agreement signed
- Ariella SolarSolar + storage Β· 327 MW Β· agreement signed
- AngelaSolar + storage Β· 60.0 MW Β· agreement signed
- Lake Alpaugh Battery StorageBattery storage Β· 10.0 MW Β· agreement signed
- MusketeersSolar + storage Β· 1,047 MW Β· in study
- SolskenSolar + storage Β· 809 MW Β· in study
- Mineral King SolarSolar + storage Β· 430 MW Β· in study
- SequoiaSolar + storage Β· 400 MW Β· in study
- Bobor StorageBattery storage Β· 152 MW Β· in study
- Rexford Solar FarmSolar + storage Β· 540 MW Β· built
- Alpaugh PV Solar Generation FacilitySolar Β· 50.0 MW Β· built
- White River PV 20MVA Solar Generation FacilitySolar Β· 20.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem