SOLAR Β· ERCOT

Markum Solar

Markum Solar is a 162 MW solar request built and operating in the ERCOT interconnection queue, in Mclennan County, Texas.

Queue statusOperating
  1. PlanningQueued Dec 2018 (completed)
  2. ConsentedJun 2021 (completed)
  3. Construction (completed)
  4. OperatingJul 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0230
Grid region
ERCOT (Texas)
Developer
Glory Leasing LLC
Connection point (POI)
177 Bosque 138kV
Location
Mclennan County, Texas
Technology
Solar: 162 MW
Total requested
162 MW
Study phase
IA
Queue status
Operational
Entered queue
17 December 2018
Agreement signed
28 June 2021
Proposed online date
September 2025
Came online
July 2024

Location

Marker shows the centre of Mclennan County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Mclennan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem