United States βΊ Grid βΊ Interconnection queues βΊ North Carolina
SOLAR Β· PJMSolar project AF2-073, Gates County
Solar project AF2-073, Gates County is a 90.0 MW solar request withdrawn in the PJM interconnection queue, in Gates County, North Carolina, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2020 (completed)
- Withdrawn / abandonedJul 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-073
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Nucor Steel-Suffolk 230 kV
- Location
- Gates County, North Carolina
- Technology
- Solar: 90.0 MW
- Total requested
- 90.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 January 2020
- Proposed online date
- March 2024
- Withdrawn
- July 2020
Location
Marker shows the centre of Gates County; the queue data does not give exact sites.
Power plants in North Carolina Β· Transmission lines in North Carolina
Other requests in Gates County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem