🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 377, Desoto County

Solar project 377, Desoto County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Desoto County, Florida, connecting to Florida Power & Light.

Queue statusOperating
  1. PlanningQueued Nov 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
377
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Orange River-Whidden 230kV
Location
Desoto County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
22 November 2019
Proposed online date
March 2024
Came online
March 2024

Location

Marker shows the centre of Desoto County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Desoto County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem