BATTERY STORAGE · ERCOT

Mineral Springs BESS

Mineral Springs BESS is a 104 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Burnet County, Texas.

Queue statusIn planning
  1. PlanningQueued Jun 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0499
Grid region
ERCOT (Texas)
Developer
Burnet County LLC
Connection point (POI)
7065 DOBVI 138kV
Location
Burnet County, Texas
Technology
Battery: 104 MW
Total requested
104 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
3 June 2024
Proposed online date
October 2026

Location

Marker shows the centre of Burnet County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Burnet County