United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· PJMSolar project AF2-006, Lackawanna County
Solar project AF2-006, Lackawanna County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Lackawanna County, Pennsylvania, connecting to PPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2019 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-006
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Jermyn Tap-Brownell 69 kV
- Location
- Lackawanna County, Pennsylvania
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 1 October 2019
- Proposed online date
- September 2021
- Withdrawn
- April 2021
Location
Marker shows the centre of Lackawanna County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Lackawanna County
- Solar project AI1-101, Lackawanna CountySolar Β· 100 MW Β· in study
- Lackawanna Thermal Generating StationGas Β· 1,000 MW Β· built
- Lackawanna Thermal Generating StationGas Β· 370 MW Β· built
- Lackawanna Thermal Generating StationGas Β· 113 MW Β· built
- ArchbaldGas Β· 44.0 MW Β· built
- Milan EnergyGas Β· 19.9 MW Β· built
- Archbald Generating StationOther Β· 9.2 MW Β· built
- ArchbaldGas Β· 6.3 MW Β· built
- Other project AE2-032, Lackawanna CountyOther Β· 811 MW Β· withdrawn
- Gas project U2-075, Lackawanna CountyGas Β· 636 MW Β· withdrawn
- Gas project B45, Lackawanna CountyGas Β· 555 MW Β· withdrawn
- Gas project AB1-108, Lackawanna CountyGas Β· 485 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem