United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J1654, Genesee County

Solar project J1654, Genesee County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Genesee County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedFeb 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1654
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Goss-Thetford 345kV Line
Location
Genesee County, Michigan
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
25 June 2020
Proposed online date
September 2023
Withdrawn
February 2023

Location

Marker shows the centre of Genesee County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Genesee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem