Solar project J3267, Genesee County

Solar project J3267, Genesee County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in Genesee County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3267
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
THETFORD
Location
Genesee County, Michigan
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
15 April 2024
Proposed online date
June 2028
Withdrawn
May 2025

Location

Marker shows the centre of Genesee County; the queue data does not give exact sites.