United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J1537, Genesee County

Solar project J1537, Genesee County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Genesee County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedDec 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1537
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Thetford #1 - Dort 138kV T-Line
Location
Genesee County, Michigan
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
23 June 2020
Proposed online date
July 2024
Withdrawn
December 2022

Location

Marker shows the centre of Genesee County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Genesee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem