SOLAR Β· ERCOT

Markum Solar 2

Markum Solar 2 is a 26.1 MW solar request withdrawn in the ERCOT interconnection queue, in Mclennan County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedSep 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0416
Grid region
ERCOT (Texas)
Developer
Glory Leasing
Connection point (POI)
177 Bosque 138kV
Location
Mclennan County, Texas
Technology
Solar: 26.1 MW
Total requested
26.1 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Entered queue
25 August 2019
Proposed online date
May 2021
Withdrawn
September 2019

Location

Marker shows the centre of Mclennan County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Mclennan County