🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

ONSHORE WIND · NYISO

North Country Wind

North Country Wind is a 298 MW onshore wind request withdrawn in the NYISO interconnection queue, in Franklin County, New York, connecting to NYPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
866
Grid region
NYISO (New York)
Utility / transmission owner
NYPA
Developer
NY North Country, LLC
Connection point (POI)
Willis - Moses 230 kV MW1
Location
Franklin County, New York
Technology
Wind: 298 MW
Total requested
298 MW
Queue status
Withdrawn
Entered queue
3 June 2019

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem