United States › Grid › Interconnection queues › New Mexico
SOLAR · SPPSolar project GEN-2014-035, Chaves County
Solar project GEN-2014-035, Chaves County is a 30.0 MW solar request built and operating in the SPP interconnection queue, in Chaves County, New Mexico, connecting to SPS.
Request details
- Queue ID
- GEN-2014-035
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Chaves County 115kV
- Location
- Chaves County, New Mexico
- Technology
- Solar: 30.0 MW
- Total requested
- 30.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 29 September 2014
- Proposed online date
- April 2023
- Came online
- April 2023
Location
Marker shows the centre of Chaves County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Chaves County
- EC500W ProjectOnshore wind · 247 MW · agreement signed
- Solar + storage project ERAS-2025-030, Chaves CountySolar + storage · 350 MW · in study
- Solar + storage project GEN-2024-271, Chaves CountySolar + storage · 250 MW · in study
- Solar project GEN-2024-311, Chaves CountySolar · 225 MW · in study
- Battery storage project GEN-2024-186, Chaves CountyBattery storage · 199 MW · in study
- Battery storage project GEN-2024-324, Chaves CountyBattery storage · 160 MW · in study
- Battery storage project GEN-2024-325, Chaves CountyBattery storage · 150 MW · in study
- Battery storage project GEN-2024-310, Chaves CountyBattery storage · 75.0 MW · in study
- Battery storage project GEN-2025-SR32, Chaves CountyBattery storage · 50.0 MW · in study
- Battery storage project GEN-2025-SR27, Chaves CountyBattery storage · 50.0 MW · in study
- Onshore wind project GEN-2008-022, Chaves CountyOnshore wind · 300 MW · built
- Onshore wind project GEN-2001-033, Chaves CountyOnshore wind · 120 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem