United States › Grid › Interconnection queues › North Dakota

ONSHORE WIND · SPP

Onshore wind project GEN-2015-096, Hettinger County

Onshore wind project GEN-2015-096, Hettinger County is a 150 MW onshore wind request built and operating in the SPP interconnection queue, in Hettinger County, North Dakota, connecting to BEPC.

Queue statusOperating
  1. PlanningQueued Oct 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-096
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Brady 230kV substation
Location
Hettinger County, North Dakota
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
19 October 2015
Proposed online date
December 2016
Came online
December 2016

Location

Marker shows the centre of Hettinger County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Hettinger County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem