ONSHORE WIND Β· MISOOnshore wind project J1480, Black Hawk County
Onshore wind project J1480, Black Hawk County is a 70.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Black Hawk County, Iowa, connecting to MIDAMERICAN ENERGY COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedApr 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1480
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY COMPANY
- Connection point (POI)
- Shawlis - Electric Farms 161kV Line
- Location
- Black Hawk County, Iowa
- Technology
- Wind: 70.0 MW
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- August 2020
- Withdrawn
- April 2020
Location
Marker shows the centre of Black Hawk County; the queue data does not give exact sites.
Other requests in Black Hawk County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem