United States › Grid › Interconnection queues › Kansas
ONSHORE WIND · SPPOnshore wind project GEN-2001-039A, Kiowa County
Onshore wind project GEN-2001-039A, Kiowa County is a 104 MW onshore wind request built and operating in the SPP interconnection queue, in Kiowa County, Kansas, connecting to MKEC.
Request details
- Queue ID
- GEN-2001-039A
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- MKEC
- Connection point (POI)
- Shooting Star Tap 115kV
- Location
- Kiowa County, Kansas
- Technology
- Wind: 104 MW
- Total requested
- 104 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 30 October 2001
Location
Marker shows the centre of Kiowa County; the queue data does not give exact sites.
Other requests in Kiowa County
- Onshore wind project GEN-2022-194, Kiowa CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2012-012, Kiowa CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2022-190, Kiowa CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2021-022, Kiowa CountyOnshore wind · 75.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem