Terra-Gen Dixie Valley Expansion (Fka Caithness Dixie Valley)

Terra-Gen Dixie Valley Expansion (Fka Caithness Dixie Valley) is a 10.0 MW geothermal request built and operating in the CAISO interconnection queue, in Churchill County, Nevada, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Jul 2004 (completed)
  2. ConsentedOct 2021 (completed)
  3. Construction (completed)
  4. OperatingMay 2006 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
33
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Bishop Control Substation 115 kV
Location
Churchill County, Nevada
Technology
Geothermal: 10.0 MW
Total requested
10.0 MW
Study phase
Executed
Queue status
Operational
Entered queue
12 July 2004
Agreement signed
11 October 2021
Proposed online date
July 1988
Came online
May 2006

Location

Marker shows the centre of Churchill County; the queue data does not give exact sites.