United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
BATTERY STORAGE Β· MISOBattery storage project J2380, Meade County
Battery storage project J2380, Meade County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Meade County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2380
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- BIG RIVERS ELECTRIC CORPORATION
- Connection point (POI)
- Meade County 161kV Substation
- Location
- Meade County, Kentucky
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 14 September 2022
- Proposed online date
- November 2027
- Withdrawn
- October 2025
Location
Marker shows the centre of Meade County; the queue data does not give exact sites.
Other requests in Meade County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem