SOLAR Β· PJMStevensburg Road Solar
Stevensburg Road Solar is a 9.3 MW solar request withdrawn in the PJM interconnection queue, in Culpeper County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedMay 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-401
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Culpeper 34.5 kV
- Location
- Culpeper County, Virginia
- Technology
- Solar: 9.3 MW
- Total requested
- 9.3 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 31 March 2020
- Proposed online date
- October 2022
- Withdrawn
- May 2021
Location
Marker shows the centre of Culpeper County; the queue data does not give exact sites.
Other requests in Culpeper County
- Greenwood SolarSolar Β· 100 MW Β· agreement signed
- Cricket SolarSolar Β· 60.0 MW Β· agreement signed
- Greenwood SolarSolar Β· 50.0 MW Β· agreement signed
- Cricket SolarSolar Β· 20.0 MW Β· agreement signed
- Maroon SolarSolar Β· 149 MW Β· suspended
- Solar project AH1-437, Culpeper CountySolar Β· 150 MW Β· withdrawn
- Solar project AC2-121, Culpeper CountySolar Β· 150 MW Β· withdrawn
- Solar project AC2-022, Culpeper CountySolar Β· 100 MW Β· withdrawn
- Solar project AC2-102, Culpeper CountySolar Β· 80.0 MW Β· withdrawn
- Battery storage project AG1-538, Culpeper CountyBattery storage Β· 75.0 MW Β· withdrawn
- Elkwood SolarSolar Β· 60.0 MW Β· withdrawn
- Battery storage project AE2-188, Culpeper CountyBattery storage Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem