ONSHORE WIND Β· PJM

Onshore wind project AB1-149, Hardy County

Onshore wind project AB1-149, Hardy County is a 122 MW onshore wind request withdrawn in the PJM interconnection queue, in Hardy County, West Virginia, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2015 (completed)
  2. Withdrawn / abandonedNov 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB1-149
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Baker 138kV
Location
Hardy County, West Virginia
Technology
Wind: 122 MW
Total requested
122 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
30 October 2015
Proposed online date
December 2018
Withdrawn
November 2016

Location

Marker shows the centre of Hardy County; the queue data does not give exact sites.