ONSHORE WIND Β· PJMOnshore wind project AB1-149, Hardy County
Onshore wind project AB1-149, Hardy County is a 122 MW onshore wind request withdrawn in the PJM interconnection queue, in Hardy County, West Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2015 (completed)
- Withdrawn / abandonedNov 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AB1-149
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Baker 138kV
- Location
- Hardy County, West Virginia
- Technology
- Wind: 122 MW
- Total requested
- 122 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 October 2015
- Proposed online date
- December 2018
- Withdrawn
- November 2016
Location
Marker shows the centre of Hardy County; the queue data does not give exact sites.
Power plants in West Virginia Β· Transmission lines in West Virginia
Other requests in Hardy County
- Short Mountain Wind EnergyOnshore wind Β· 80.0 MW Β· suspended
- Solar project AG2-404, Hardy CountySolar Β· 250 MW Β· withdrawn
- Solar project AG2-403, Hardy CountySolar Β· 125 MW Β· withdrawn
- Onshore wind project Y1-016, Hardy CountyOnshore wind Β· 50.0 MW Β· withdrawn
- Onshore wind project R21, Hardy CountyOnshore wind Β· 14.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem