πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AH1-668, Centre County

Solar project AH1-668, Centre County is a 19.9 MW solar request withdrawn in the PJM interconnection queue, in Centre County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2020 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-668
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Developer
Millheim Solar I, LLC
Connection point (POI)
Madisonburg Jct-Millheim 46 kV
Location
Centre County, Pennsylvania
Technology
Solar: 19.9 MW
Total requested
19.9 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
29 September 2020
Proposed online date
August 2022
Withdrawn
March 2025

Location

Marker shows the centre of Centre County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Centre County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem