πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

BATTERY STORAGE Β· MISO

Battery storage project J2217, Lee County

Battery storage project J2217, Lee County is a 50.0 MW battery storage request withdrawn in the MISO interconnection queue, in Lee County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2217
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
Brinkley East - Aubrey 230 kV Line
Location
Lee County, Arkansas
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
21 December 2021
Proposed online date
October 2024
Withdrawn
November 2023

Location

Marker shows the centre of Lee County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Lee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem