🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › North Carolina

SOLAR · SOUTHEAST

Solar project 977892, Warren County

Solar project 977892, Warren County is a 5.0 MW solar request in interconnection study in the Southeast interconnection queue, in Warren County, North Carolina, connecting to Duke Energy Progress.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
977892
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
WARRENTON 115KV
Location
Warren County, North Carolina
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Other
Study phase
Phase 1 Cluster Study - Study Complete
Queue status
Active
Entered queue
30 June 2025

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem