Solar + storage project C2-181, Lake County

Solar + storage project C2-181, Lake County is a 80.0 MW solar + storage request in interconnection study in the West interconnection queue, in Lake County, Oregon, connecting to PacifiCorp.

Queue statusIn planning
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
C2-181
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Summer Lake substation
Location
Lake County, Oregon
Technology
Solar: 80.0 MW · Battery
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Active
Entered queue
15 May 2022
Proposed online date
October 2026

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem