Solar project SGI-PNM-2013-02, Valencia County

Solar project SGI-PNM-2013-02, Valencia County is a 9.0 MW solar request built and operating in the West interconnection queue, in Valencia County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusOperating
  1. PlanningQueued May 2013 (completed)
  2. ConsentedDec 2013 (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
SGI-PNM-2013-02
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
PNM-GPD Meadow Lake El Cerro Feeder 11
Location
Valencia County, New Mexico
Technology
Solar: 9.0 MW
Total requested
9.0 MW
Service type
Network resource (NRIS)
Study phase
SGIA executed 12/19/2013.
Queue status
Operational
Entered queue
15 May 2013
Agreement signed
19 December 2013

Location

Marker shows the centre of Valencia County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Valencia County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem