United States › Grid › Interconnection queues › Illinois
BATTERY STORAGE · MISOBattery storage project J3968, Coles County
Battery storage project J3968, Coles County is a 100 MW battery storage request in interconnection study in the MISO interconnection queue, in Coles County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3968
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Mattoon West
- Location
- Coles County, Illinois
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 14 March 2025
- Proposed online date
- September 2028
Location
Marker shows the centre of Coles County; the queue data does not give exact sites.
Other requests in Coles County
- Solar project J1232, Coles CountySolar · 99.0 MW · agreement signed
- Wind + storage project J2128, Coles CountyWind + storage · 300 MW · in study
- Solar project J3012, Coles CountySolar · 287 MW · in study
- Onshore wind project J3391, Coles CountyOnshore wind · 200 MW · in study
- Solar project J949, Coles CountySolar · 200 MW · built
- Coal project G661, Coles CountyCoal · 726 MW · withdrawn
- Onshore wind project J1757, Coles CountyOnshore wind · 300 MW · withdrawn
- Battery storage project J2504, Coles CountyBattery storage · 300 MW · withdrawn
- Onshore wind project J973, Coles CountyOnshore wind · 250 MW · withdrawn
- Solar project J2393, Coles CountySolar · 164 MW · withdrawn
- Solar project J1974, Coles CountySolar · 160 MW · withdrawn
- Battery storage project J1975, Coles CountyBattery storage · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem