Onshore wind project 123, Converse County

Onshore wind project 123, Converse County is a 13.0 MW onshore wind request withdrawn in the West interconnection queue, in Converse County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2007 (completed)
  2. Withdrawn / abandonedNov 2009 (project stopped here)
  3. ConsentedMay 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
123
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp Commercial & Trading
Connection point (POI)
Windstar substation
Location
Converse County, Wyoming
Technology
Wind: 13.0 MW
Total requested
13.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed 5/29/08, IA withdrawn 11/5/09
Queue status
Withdrawn
Entered queue
5 March 2007
Agreement signed
29 May 2008
Proposed online date
March 2008
Withdrawn
November 2009

Location

Marker shows the centre of Converse County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Converse County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem