United States βΊ Grid βΊ Interconnection queues βΊ California
SOLAR Β· CAISOPV-41
PV-41 is a 100 MW solar request withdrawn in the CAISO interconnection queue, in San Luis Obispo County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2008 (completed)
- Withdrawn / abandonedNov 2008 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 355
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- San Luis Obispo-Tremblor 115kV line
- Location
- San Luis Obispo County, California
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 28 April 2008
- Proposed online date
- May 2011
- Withdrawn
- November 2008
Location
Marker shows the centre of San Luis Obispo County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in San Luis Obispo County
- Windwalker OffshoreOffshore wind Β· 1,029 MW Β· agreement signed
- California Valley Solar Ranch (Fka Carrizo Solar Farm II)Solar Β· 250 MW Β· built
- California Valley PVSolar Β· 210 MW Β· built
- Carrizo Plain SolarSolar Β· 190 MW Β· built
- Desert Topaz PV 2Solar Β· 150 MW Β· built
- Caballero StorageBattery storage Β· 106 MW Β· built
- Diablo Canyon P.P. Unit 2Gas Β· 45.0 MW Β· built
- Cuyama SolarSolar Β· 40.0 MW Β· built
- Diablo Canyon P.P. Unit 1Nuclear Β· 37.0 MW Β· built
- IslayWind + storage Β· 2,275 MW Β· withdrawn
- Vinson EnergyWind + storage Β· 1,887 MW Β· withdrawn
- Nimitz 2 GenerationWind + storage Β· 1,887 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem