United States β€Ί Grid β€Ί Interconnection queues β€Ί Delaware

SOLAR Β· PJM

Solar project AC2-183, Sussex County

Solar project AC2-183, Sussex County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Sussex County, Delaware, connecting to DPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2017 (completed)
  2. Withdrawn / abandonedMay 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AC2-183
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Pepper 69kV
Location
Sussex County, Delaware
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 March 2017
Proposed online date
December 2018
Withdrawn
May 2017

Location

Marker shows the centre of Sussex County; the queue data does not give exact sites.

Power plants in Delaware Β· Transmission lines in Delaware

Other requests in Sussex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem