United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
BATTERY STORAGE Β· SPPBattery storage project GEN-2024-163, Garvin County
Battery storage project GEN-2024-163, Garvin County is a 199 MW battery storage request withdrawn in the SPP interconnection queue, in Garvin County, Oklahoma, connecting to OGE.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2024-163
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Chigley 138 kV Substation
- Location
- Garvin County, Oklahoma
- Technology
- Battery: 199 MW
- Total requested
- 199 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 1 March 2025
- Proposed online date
- January 2030
Location
Marker shows the centre of Garvin County; the queue data does not give exact sites.
Other requests in Garvin County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem