United States βΊ Grid βΊ Interconnection queues βΊ Louisiana
SOLAR + STORAGE Β· MISOSolar + storage project J2804, West Carroll Parish County
Solar + storage project J2804, West Carroll Parish County is a 100 MW solar + storage request withdrawn in the MISO interconnection queue, in West Carroll Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2804
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Oak Grove - Galion 115kV Tap
- Location
- West Carroll Parish County, Louisiana
- Technology
- Solar: 100 MW Β· Battery
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 15 September 2022
- Proposed online date
- June 2017
- Withdrawn
- July 2025
Location
Marker shows the centre of West Carroll Parish County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in West Carroll Parish County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem