COAL Β· SOUTHEAST

Coal project 1

Coal project 1 is a 750 MW coal request built and operating in the Southeast interconnection queue, connecting to Seminole Electric Cooperative.

Queue statusOperating
  1. PlanningQueued Sep 2003 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget May 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Seminole Electric Cooperative
Connection point (POI)
SGS Switchyard
Location
Florida
Technology
Coal: 750 MW
Total requested
750 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: System Impact; Status: Complete
Queue status
Operational
Entered queue
17 September 2003
Proposed online date
May 2012

Location

No county location in the queue data.

Power plants in Florida Β· Transmission lines in Florida