United States βΊ Grid βΊ Interconnection queues βΊ Oregon
ONSHORE WIND Β· WESTShepherds Flat Wind
Shepherds Flat Wind is a 250 MW onshore wind request withdrawn in the West interconnection queue, in Morrow County, Oregon, connecting to Shepherds Flat Wind, LLC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2002 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G110
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Shepherds Flat Wind, LLC
- Developer
- Shepherds Flat Wind, LLC
- Connection point (POI)
- BPA Slatt 500 kV Substation
- Location
- Morrow County, Oregon
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 18 September 2002
- Proposed online date
- October 2003
Location
Marker shows the centre of Morrow County; the queue data does not give exact sites.
Other requests in Morrow County
- Solar project G0678, Morrow CountySolar Β· 1,200 MW Β· in study
- Gas project G0752, Morrow CountyGas Β· 670 MW Β· in study
- Battery storage project G0963, Morrow CountyBattery storage Β· 650 MW Β· in study
- Solar + storage project T2-008, Morrow CountySolar + storage Β· 500 MW Β· in study
- Solar + storage project G0478, Morrow CountySolar + storage Β· 500 MW Β· in study
- Solar + storage project T2-031, Morrow CountySolar + storage Β· 400 MW Β· in study
- Solar + storage project T2-087, Morrow CountySolar + storage Β· 400 MW Β· in study
- Solar + storage project T2-030, Morrow CountySolar + storage Β· 400 MW Β· in study
- Solar + storage project T2-086, Morrow CountySolar + storage Β· 400 MW Β· in study
- Onshore wind project G0366, Morrow CountyOnshore wind Β· 302 MW Β· in study
- Solar project G0944, Morrow CountySolar Β· 261 MW Β· in study
- Onshore wind project G0435, Morrow CountyOnshore wind Β· 238 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem