Solar project IC-672, Coffee County

Solar project IC-672, Coffee County is a 79.7 MW solar request withdrawn in the Southeast interconnection queue, in Coffee County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2018 (completed)
  2. Withdrawn / abandonedOct 2021 (project stopped here)
  3. ConsentedOct 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-672
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
South Enterprise TS 115 kV Bus
Location
Coffee County, Alabama
Technology
Solar: 79.7 MW
Total requested
79.7 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
13 February 2018
Agreement signed
1 October 2019
Withdrawn
October 2021

Location

Marker shows the centre of Coffee County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Coffee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem