SOLAR + STORAGE Β· SOUTHEASTSolar + storage project IC-897, Coffee County
Solar + storage project IC-897, Coffee County is a 80.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Coffee County, Alabama, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2020 (completed)
- Withdrawn / abandonedApr 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-897
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- South Enterprise Substation 115 kV Bus
- Location
- Coffee County, Alabama
- Technology
- Solar: 80.0 MW Β· Battery
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 14 August 2020
- Proposed online date
- February 2025
- Withdrawn
- April 2025
Location
Marker shows the centre of Coffee County; the queue data does not give exact sites.