SOLAR Β· PJM

Solar project W4-096, Wicomico County

Solar project W4-096, Wicomico County is a 10.0 MW solar request withdrawn in the PJM interconnection queue, in Wicomico County, Maryland, connecting to DPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2011 (completed)
  2. Withdrawn / abandonedFeb 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
W4-096
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Piney Grove 25kV
Location
Wicomico County, Maryland
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 January 2011
Proposed online date
March 2013
Withdrawn
February 2011

Location

Marker shows the centre of Wicomico County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Wicomico County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem