SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2022-172, Dawson County

Solar + storage project GEN-2022-172, Dawson County is a 140 MW solar + storage request withdrawn in the SPP interconnection queue, in Dawson County, Nebraska, connecting to NPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-172
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Canaday 230 kV Substation
Location
Dawson County, Nebraska
Technology
Solar: 140 MW Β· Battery
Total requested
140 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
26 February 2023
Proposed online date
May 2027
Withdrawn
November 2023

Location

Marker shows the centre of Dawson County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Dawson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem