SOLAR Β· PJM

Solar project AG2-672, Sussex County

Solar project AG2-672, Sussex County is a 8.0 MW solar request withdrawn in the PJM interconnection queue, in Sussex County, Delaware, connecting to DPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedAug 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-672
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Conaway 138 kV
Location
Sussex County, Delaware
Technology
Solar: 8.0 MW
Total requested
8.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 March 2021
Proposed online date
September 2023
Withdrawn
August 2022

Location

Marker shows the centre of Sussex County; the queue data does not give exact sites.

Power plants in Delaware Β· Transmission lines in Delaware

Other requests in Sussex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem