SOLAR + STORAGE Β· MISO

Solar + storage project J2318, Warren County

Solar + storage project J2318, Warren County is a 75.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Warren County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2022 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2318
Grid region
MISO (Midcontinent)
Utility / transmission owner
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Connection point (POI)
North East (Castle) - Culley 138 kV (J1642 POI)
Location
Warren County, Indiana
Technology
Solar: 75.0 MW Β· Battery
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
28 March 2022
Proposed online date
October 2025
Withdrawn
October 2024

Location

Marker shows the centre of Warren County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Warren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem