United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR + STORAGE Β· MISOSolar + storage project J2318, Warren County
Solar + storage project J2318, Warren County is a 75.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Warren County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2022 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2318
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
- Connection point (POI)
- North East (Castle) - Culley 138 kV (J1642 POI)
- Location
- Warren County, Indiana
- Technology
- Solar: 75.0 MW Β· Battery
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 28 March 2022
- Proposed online date
- October 2025
- Withdrawn
- October 2024
Location
Marker shows the centre of Warren County; the queue data does not give exact sites.
Other requests in Warren County
- Onshore wind project U1-024, Warren CountyOnshore wind Β· 500 MW Β· withdrawn
- Onshore wind project AD2-138, Warren CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J083, Warren CountyOnshore wind Β· 200 MW Β· withdrawn
- Battery storage project AH1-502, Warren CountyBattery storage Β· 150 MW Β· withdrawn
- Solar + storage project J2615, Warren CountySolar + storage Β· 145 MW Β· withdrawn
- Onshore wind project J1774, Warren CountyOnshore wind Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem