ONSHORE WIND Β· WEST

Onshore wind project 318, Lake County

Onshore wind project 318, Lake County is a 103 MW onshore wind request withdrawn in the West interconnection queue, in Lake County, Oregon, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
318
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Line from proposed project site to the Ponderosa substation
Location
Lake County, Oregon
Technology
Wind: 103 MW
Total requested
103 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
4 February 2010
Proposed online date
December 2012

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Lake County