United States › Grid › Interconnection queues › California

SOLAR · CAISO

Atwell Island PV Solar Generating Facility

Atwell Island PV Solar Generating Facility is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in Tulare County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Apr 2008 (completed)
  2. ConsentedNov 2010 (completed)
  3. Construction (completed)
  4. OperatingMar 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
340
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Smyrna-Alpaugh 115kV line
Location
Tulare County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
22 April 2008
Agreement signed
18 November 2010
Proposed online date
May 2010
Came online
March 2013

Location

Marker shows the centre of Tulare County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Tulare County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem