United States βΊ Grid βΊ Interconnection queues βΊ Texas
OTHER Β· ERCOTGold Rush Energy Storage
Gold Rush Energy Storage is a 201 MW other request withdrawn in the ERCOT interconnection queue, in Mills County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2023 (completed)
- Withdrawn / abandonedDec 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 26INR0199
- Grid region
- ERCOT (Texas)
- Developer
- Goldthwaite Energy Storage, LLC
- Connection point (POI)
- 7070 Goldthwaite Substation 138kV
- Location
- Mills County, Texas
- Technology
- Other: 201 MW
- Total requested
- 201 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 13 August 2023
- Proposed online date
- December 2026
- Withdrawn
- December 2023
Location
Marker shows the centre of Mills County; the queue data does not give exact sites.
Other requests in Mills County
- Priddy WindOnshore wind Β· 302 MW Β· agreement signed
- Clapton StorageSolar + storage Β· 209 MW Β· in study
- Clapton SolarSolar + storage Β· 201 MW Β· in study
- Cash Mills Storage CenterBattery storage Β· 201 MW Β· in study
- Starlight SolarSolar + storage Β· 131 MW Β· in study
- Starlight StorageSolar + storage Β· 105 MW Β· in study
- Castle Corral BESSBattery storage Β· 201 MW Β· suspended
- Aguayo WindOnshore wind Β· 196 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem