πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

Aguayo Wind

Aguayo Wind is a 196 MW onshore wind request built and operating in the ERCOT interconnection queue, in Mills County, Texas.

Queue statusOperating
  1. PlanningQueued Feb 2019 (completed)
  2. ConsentedApr 2022 (completed)
  3. Construction (completed)
  4. OperatingOct 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0250
Grid region
ERCOT (Texas)
Developer
Castle Gap Wind Power
Connection point (POI)
tap 345kV 1444 Brown - 3422 Killeen
Location
Mills County, Texas
Technology
Wind: 196 MW
Total requested
196 MW
Study phase
IA
Queue status
Operational
Entered queue
4 February 2019
Agreement signed
29 April 2022
Proposed online date
September 2023
Came online
October 2023

Location

Marker shows the centre of Mills County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Mills County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem