Onshore wind project 126, Converse County

Onshore wind project 126, Converse County is a 239 MW onshore wind request built and operating in the West interconnection queue, in Converse County, Wyoming, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Mar 2007 (completed)
  2. ConsentedMay 2008 (completed)
  3. Construction (completed)
  4. OperatingTarget Jan 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
126
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp Commercial & Trading
Connection point (POI)
Windstar substation near Dave Johnston Plant
Location
Converse County, Wyoming
Technology
Wind: 239 MW
Total requested
239 MW
Service type
Energy only (ERIS)
Study phase
IA signed May 29, 2008
Queue status
Operational
Entered queue
5 March 2007
Agreement signed
29 May 2008
Proposed online date
January 2009

Location

Marker shows the centre of Converse County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Converse County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem