Solar project 749, Walla Walla County

Solar project 749, Walla Walla County is a 40.0 MW solar request withdrawn in the West interconnection queue, in Walla Walla County, Washington, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
749
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Wallula substation
Location
Walla Walla County, Washington
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
20 May 2016
Proposed online date
December 2018

Location

Marker shows the centre of Walla Walla County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Walla Walla County